EVALUASI WAKTU PELAKSANAAN DAN BIAYA DENGAN EARNED VALUE MANAGEMENT (EVM) MENGGUNAKAN MICROSOFT PROJECT PADA PROYEK REHABILITASI RUAS JALAN KRANGGAN–NGAJUM, KABUPATEN MALANG

Nadya Al Rizani, Ita Suhermin Ingsih, Ruli Saefudin

Abstract


The Kranggan–Ngajum Road Rehabilitation Project in Malang Regency, with a contract value of IDR 287,204,400 and a planned duration of 16 weeks (112 calendar days), showed discrepancies between planned and actual Time and Cost performance. This study evaluates project performance using the Earned Value Management (EVM) method assisted by Microsoft Project. The results showed that the project experienced delays from weeks 1 to 10 (SPI < 1), with the largest delay in week 8 (SV = -IDR 24,878,935.37), but successfully caught up with the Schedule from weeks 11 to 16. Cost performance improved from CPI < 1 to CPI = 1.06 at project completion. The final EAC value of IDR 271,679,839.00 was IDR 15,524,561.00 (5.41%) lower than the contract value, indicating Cost savings. The project was completed on Time with efficient Cost performance.

References


Direktorat Jendral Bina Marga, “Direktorat Jenderal Bina Marga. (2023). Direktorat Jenderal Bina Marga – Statistik Jalan dan Jembatan Tahun 2023.” 2023.

Y. Pradana and I. S. Ingsih, “Analisis Manjemen Risiko Menggunakan Metode FTA dan FMEA Pada Pekerjaan Kolam Retensi dan Rumah Pompa Proyek Pembangunan Jalan Tol Semarang-Demak Paket 1C,” 2025.

R. Widyarso, B. Witjaksana, and J. Purnama, “Analysis of Time and Cost Performance in Construction Projects Using the Earned Value Management Method,” vol. 4, no. 4, 2025.

Project Management Institute, Project Management Institute-A Guide to the Project Management Body of Knowledge PMBOK R Guide PMBOK®️-Guide Project Management Institute 2021, 7th ed. Newtown Square, PA: Project Management Institute, 2021.

R. A. Pribadi and M. Abduh, “Analisis Cost Performance Index (CPI) dan Schedule Performance Index (SPI) Menggunakan Metode Earned Value (Studi Kasus Pada Proyek Pembangunan Gedung Pasar Bucor Kulon Kabupaten Probolinggo),” J. Media Tek. Sipil, vol. 20, no. 1, pp. 14–23, Feb. 2022, doi: 10.22219/jmts.v20i1.14620.

H. A. Siva and I. Junita, “Evaluasi Kinerja Proyek Perumahan Rakyat di Kabupaten Bandung Barat dengan Menggunakan Earned Value Management (EVM) dan Visualisasi Kurva ‘S,’” J. Integr. Syst., vol. 8, no. 1, pp. 75–88, Jun. 2025, doi: 10.28932/jis.v8i1.11568.

Y. Syahrir, J. Jusmidah, and H. Haerianti, “Evaluasi Manajemen Waktu dan Biaya Pada Proyek Peningkatan Ruas Jalan Paket 4 Menggunakan Metode Earned Value,” J. Ilm. Ecosyst., vol. 25, no. 1, pp. 72–84, Apr. 2025, doi: 10.35965/eco.v25i1.5783.

S. Suparno, H. Teki Tjendani, and B. Witjaksana, “Analysis of Cost and Schedule Variances Using Earned Value Method on Waru - Buduran Frontage Road Bridge Construction Project,” Asian J. Eng. Soc. Health, vol. 4, no. 2, pp. 288–297,Feb 2025, doi: 10.46799/ajesh.v4i2.528.

A. Nurdiana, “Analisis Biaya Tidak Langsung Pada Proyek Pembangunan Best Western Star Hotel & Star Apartemen Semarang,” Teknik, vol. 36, no. 2, pp. 105–109, Dec. 2015, doi: 10.14710/teknik.v36i2.8906.


Refbacks

  • There are currently no refbacks.